Rear and side-return extensions in London

Party wall notices for rear extensions

For a London rear or side-return extension, check where the new wall will sit, whether the work touches an existing shared wall, and how deep your foundations will go. Each can affect whether you need to serve notice.

Planning building work Party wall notices for rear extensions

Three checks for an extension

  1. Where will the new wall sit? A wall built at the boundary can call for a notice under section 1. Building a new wall astride the boundary requires your neighbour’s written consent. Building wholly on your land at the line of junction can still require notice.
  2. Will the extension use a shared wall? Cutting into an existing party wall for a beam or altering that wall can trigger the section 2 procedure.
  3. How deep are the foundations? Excavation within three metres of a neighbouring building can require notice if the proposed excavation goes below the bottom of its foundations. Some deeper excavations within six metres can also qualify. This can apply even when the homes are detached, since the excavation test depends on distance and foundation depth.
A gloved hand laying a brick on a wall under construction

An example on a London terrace

Imagine a side-return extension with a new wall wholly on your side but right up to the boundary. The engineer also specifies foundations within three metres of your neighbour’s rear addition. You would need to check the boundary wall and the excavation separately. If a steel beam is also to bear into the existing party wall, that is a third point to review.

Ask your designer to identify each issue on the drawings. One project can involve different notices, with different lead times.

What to have ready

  • A site plan that identifies the boundary and adjoining buildings.
  • Existing and proposed ground-floor plans, plus elevations showing the new wall.
  • Foundation sections with proposed depths and distances, and any notes on neighbouring foundations.
  • Structural details showing anything cut into or supported by an existing shared wall.

Allow at least one month for applicable boundary or excavation notices and normally at least two months for a party structure notice. Read the party wall notice overview for the next step.

Official guidance

GOV.UK explanatory booklet · Section 1 of the Party Wall etc. Act 1996 · Section 3 of the Party Wall etc. Act 1996 · Section 6 of the Party Wall etc. Act 1996