Received a party wall notice?

Check when the notice was served, keep a copy and look at the proposed work and any drawings. Your next step depends on the type of notice and whether you’re comfortable with the proposal.

See your response options

Check the date first. For party structure and excavation notices, the 14-day period starts on the day the notice is served. If there’s no written consent in that period, a dispute is treated as having arisen under the Act. If your neighbour proposes a new wall astride the boundary, silence does not give them consent to build it across the line. If you’re unsure which notice you have or the date is close, get advice promptly.

What to check first

  • Keep the notice and record when and how it arrived.
  • Review the works described and the proposed start date. Keep any attached plans and sections.
  • Identify the areas of your property that could be affected, and make a note of any concerns you want to raise.

Your response options

Consent in writing. If you are comfortable with the proposal, you can normally give written consent. You can discuss arranging a record of the existing condition before work starts.

Dissent. Where this brings the Act’s dispute procedure into play, the owners can agree to appoint one surveyor or make separate appointments. Any surveyor appointed under the Act must deal with the dispute impartially.

If the 14 days have passed. Check whether you have received a separate written request to appoint a surveyor. If a dispute has arisen and you fail to appoint within 10 days of that request being served, the other owner may appoint one on your behalf. See section 10 of the Act.

No notice, or work already under way?

Ask your neighbour what work is planned or has started, and request any relevant drawings. Keep dated photos of the affected areas of your home and copies of correspondence. If work is already under way and you believe notice was required, get prompt advice about your options. If you are considering formal steps to stop work, seek legal advice.

Who pays for a surveyor?

The owner carrying out the work usually pays the reasonable surveyors’ costs for work that is for their benefit. How costs are allocated can depend on the circumstances and may be determined in the award.

See how a schedule of condition documents the parts of your property that may be affected.