Planning building work in London
Party wall guide for building owners
Use this guide before you agree a start date with your builder. It sets out what to check on your drawings, who to notify, and how your neighbours’ responses affect what happens next.
Start with the drawings
Ask your architect or structural engineer to show the boundaries, any work to an existing shared wall and the depth of new foundations relative to nearby buildings. A single project can fall into more than one category.

| Check | What to look for on the drawings | Notice period |
|---|---|---|
| New wall at the boundary Section 1 | A new wall on the boundary line, either wholly on your land or intended to straddle the boundary. A new wall straddling the line requires your neighbour’s written consent. | 1 month |
| Work to an existing party structure Sections 2 and 3 | Beam pockets cut into a shared wall, raising or rebuilding that wall, or removing a chimney breast from it. | 2 months |
| Excavation near a neighbouring structure Section 6 | A proposed excavation within three metres that goes below the adjoining foundations, or work within six metres that meets the Act’s 45-degree test. | 1 month |
A rear extension could need both a boundary-wall notice and an excavation notice. If a steel beam also bears into an existing party wall, check whether you need a party structure notice with the longer lead time.
Prepare and serve the right notice
- Identify the adjoining owners. The person living next door may be one of several people to notify. A property divided into flats can have a freeholder and relevant leaseholders. Check who qualifies under the Act for the part of the building affected.
- Get the current drawing set. Keep the site plan, proposed floor plans, elevations and relevant structural sections together. For an excavation notice, the plans and sections must show where you propose to dig and how deep.
- Explain the work to your neighbour. Share a simple summary and the relevant drawings before serving formal notice if you can. Give an expected start date and flag anything likely to affect their property.
- Keep a record of service. Save a copy of each notice and record who received it, how it was served and when. Email can be used where the recipient has agreed to electronic service and provided an email address for it.
Planning permission and building regulations have their own requirements. Check the party wall process alongside them when you put together your programme.
What happens after you serve notice?
Written consent
Keep a copy with your project records. Check the applicable notice period and any conditions before starting. You and your neighbour can discuss making a record of the existing condition.
Dissent or no reply
For party structure and excavation notices, a dispute generally arises if there is no written consent within 14 days of service. If the dispute procedure applies, the owners can agree on one surveyor or appoint separate surveyors to make an award. A new wall intended to straddle the boundary follows a different rule: without the required written consent, the wall must be built wholly on your own land.
Where an award is needed, allow time for any site inspection and for the award to be made and served before the work it covers begins. See what a party wall award or a schedule of condition covers.
Before you confirm a start date
- Check the notice type, recipient and date of service for each affected property. If the start has slipped, check whether the notice still applies. Party structure and excavation notices cease to have effect if the relevant works have not begun within 12 months of service.
- Keep written replies and check whether any award or site visit is outstanding.
- Give the builder the current drawings and any conditions that affect the work.
- If the design changes after notice is served, keep the old and new drawings and have the changes reviewed before relying on the original notice or award.
Have your postcode, drawings and proposed start date to hand if you contact us about your project.
Find the guide for your project
Rear extensions
Check the boundary, shared walls and foundation depths before you set a start date.
Read the rear extension guideLoft conversions
Find out what to look for in steel beam details, roof drawings and chimney plans.
Read the loft conversion guideBasement excavation
Understand the three- and six-metre excavation checks and the plans that support them.
Read the basement excavation guideOfficial guidance
GOV.UK guide to the Party Wall etc. Act 1996 · How to serve notices under section 15.