Basement works in London
Party wall notices for basement excavation
For a new or deeper London basement, start with a dimensioned section. How far the excavation is from neighbouring structures, how deep it goes and whether a shared wall will be underpinned can all change the party wall requirements.
The three- and six-metre checks
Within three metres. Section 6 can apply if the excavation is within three metres of an adjoining owner’s building or structure and goes below the bottom of its foundations within that distance.
Within six metres. A second test applies if the proposed work meets a plane drawn downwards at 45 degrees from where the bottom of the adjoining foundations meets the outside face of that structure. An engineer’s dimensioned section helps show whether this test is met.
The measurement is to the adjoining building or structure. Identify potentially affected structures on the site plan, even where they are set back from the boundary.
Check for work to the shared wall as well
Underpinning or other work to an existing party wall may involve a separate party structure notice. When section 6 applies, the excavation notice must describe the work and state whether you propose to underpin, strengthen or safeguard the adjoining foundations. It must be accompanied by plans and sections showing the site and depth of the excavation and, where relevant, the site of the new structure.
Section 6 generally requires at least one month’s notice. A party structure notice generally requires at least two months. Factor in time for surveyor appointments and an award if a dispute arises.
What to have ready
- A dimensioned site plan with nearby buildings and structures marked.
- Existing and proposed sections with excavation depth, levels and known neighbouring foundation depths.
- Structural drawings and any outline information from the engineer on sequencing or temporary support.
- Any existing notices or written responses and your proposed start date.
If you do not know the depth of neighbouring foundations, flag that when you first discuss the drawings. If the design proposes special foundations on your neighbour’s land, section 7 requires their prior written consent. A schedule of condition can also help document relevant areas before work starts.
Official guidance
GOV.UK explanatory booklet · Section 2 of the Party Wall etc. Act 1996 · Section 3 of the Party Wall etc. Act 1996 · Section 6 of the Party Wall etc. Act 1996